The Project is expected to be implemented as follows:
A. Investors conference – 20-21 January 2010
B. Receipt of expressions of interest – 29 January 2010
C. Announcement of short-listed bidders – 18 February 2010
D. Issue of Draft Request for Proposals – March/April 2010
E. Issue of Full Request for Proposals – July 2010
F. Selection & Announcement of winning bidder – September 2010